1. first put through a three-phase power switch, and then open the main power switch on the side control box, if there is a high frequency switch, not to play, then play electric power switch on, at this time, vacuum tubes and hot model began to warm up. 2. on lower secondary insulation, extreme loading mode, press the test switch, start debugging the mold junction location, if the joint is bad, mobile module, if the level of fit, adjust the four pillars of the upper die. 3. mold after a tune up, three time controller (if it is a pedal type machine, only high frequency welding time), fall time last run mode to time mode under the press, welding time is time, cooling time, curing time, three of the necessary flexibility, there is no fixed number.